On most new homes and renovations, the builder is not paid all at once. Money is released in stages, called draws, as work is completed. Understanding how draws work is one of the best ways an owner can protect a project, because the draw process is where overpayment, unpaid subcontractors and budget drift either get caught or slip through.
This guide describes how draw processes commonly work. It is general education, not legal or lending advice. Your contract and, if you use financing, your lender's requirements control.
What a draw schedule is
A draw schedule is a list of payment milestones tied to construction progress. A simple residential schedule might look like this (the percentages are an example, not a standard):
| Milestone | Example share of contract | What "complete" should mean |
|---|---|---|
| Deposit or mobilization | 5% | Permit issued, contract signed, insurance in place |
| Foundation | 10% | Foundation complete and inspected |
| Framing and roof | 20% | Structure dried in, framing inspection passed |
| Rough-ins | 15% | Plumbing, electrical and HVAC rough-ins inspected |
| Insulation and drywall | 15% | Insulation inspected, drywall hung and finished |
| Trim and finishes | 20% | Cabinets, trim, flooring, fixtures installed |
| Final | 15% | Final inspections passed, certificate of occupancy, punch list complete |
Two principles matter more than the exact percentages. First, payments should not run ahead of the value of work in place; front-loaded schedules leave the owner exposed if the builder stops. Second, every milestone needs a definition of "complete" that both sides can verify.
Use our construction draw schedule calculator to map your contract amount to milestones and see retainage held at each stage.
How a draw request is typically processed
- The builder submits a draw request listing the work completed, usually by budget line, with invoices for materials and subcontractors.
- Someone verifies the work. If a lender is involved, it usually sends an inspector. If you are paying cash, you or your representative should walk the site and compare progress with the request.
- Lien waivers are collected from the builder and, ideally, from major subcontractors and suppliers paid from the previous draw.
- Funds are released, less any retainage.
- The budget is updated: what has been paid, what remains, and whether the remaining funds are enough to finish.
Lien waivers and North Carolina's lien agent system
In North Carolina, contractors, subcontractors and suppliers who are not paid can, in some circumstances, file liens against the property, even if the owner paid the general contractor. Lien waivers are written statements from the people being paid that they have received payment for work through a date.
North Carolina also requires owners of most projects costing $40,000 or more to designate a lien agent before contracting for the work (G.S. 44A-11.1). Improvements to an existing single-family home occupied by the owner are exempt. The appointment is filed through LiensNC and posted at the job site. Subcontractors and suppliers send notices to the lien agent, which gives the owner and closing attorneys visibility into who is working on the project. Ask your attorney how to use those notices when you approve draws.
Retainage
Retainage is a percentage held back from each payment until the work is substantially complete and the punch list is finished. It gives the owner leverage to get the last items done. The amount and release terms are set by contract; ask your attorney what North Carolina law allows for your type of project.
Change orders
Change orders are the most common way a fixed budget becomes an open-ended one. Protect the budget by:
- Requiring every change in writing, with price and schedule impact, signed before the work is done.
- Tracking approved change orders in the budget so the contract total stays current.
- Separating owner-requested changes from builder-caused corrections, which should not be paid as changes.
- Watching allowance overages, which behave like change orders even when nobody calls them that.
Five warning signs in a draw request
- The request is ahead of what you can see on site.
- Lien waivers from the last draw are missing or only from the builder.
- Line items are being moved between budget categories without explanation.
- Contingency is being used early for things that look like scope gaps.
- The "cost to complete" does not reconcile with the remaining budget.
The owner's monthly checklist
- Walk the site and photograph progress before approving a draw.
- Check inspections passed against the permit record.
- Collect lien waivers for the previous payment.
- Update the budget: paid to date, approved changes, remaining contingency, cost to complete.
- Confirm the schedule and any material lead times.
Our budget and draw-schedule planning service sets this up before construction starts and, if you want, reviews draw requests with you during the build. Cresari does not hold, disburse or manage funds, and it does not act as a lender or contractor.
Frequently asked questions
How many draws are typical on a home build?
There is no fixed number; the contract sets it. Schedules are usually built around visible stages such as foundation, framing, rough-ins, drywall and finishes. Our calculator's seven-milestone example is a starting point, not a standard.
What is the difference between conditional and unconditional lien waivers?
A conditional waiver takes effect only when the payment it covers is actually received; an unconditional waiver is effective when signed. Ask your attorney which forms to use.
What should I do if the builder asks for money ahead of the schedule?
Ask what the money is for and compare it with work in place. Paying ahead of progress increases your risk; if materials must be bought early, document them and, where possible, pay against delivery.
Who files the lien agent appointment?
The owner designates the lien agent, usually through the LiensNC system, no later than when the owner first contracts for the improvements, for projects of $40,000 or more.
Does a passed county inspection mean I should pay the draw?
Not by itself. The building inspection checks code compliance. Before paying, confirm the work matches the milestone definition and quality standards and that prior lien waivers are in.
When is retainage released?
When the contract says, usually at substantial completion and after the punch list is finished and final lien waivers are received.
This guide is educational and is not legal, tax, lending or financial advice. Rules, fees and processes change; confirm current requirements with the office or professional named. Talk to a licensed professional about your situation.